MEES benchmarking across 200 shopping centre units

Every unit in the UK's third largest indoor shopping centre brought to EPC compliance ahead of the deadline.

200EPCs delivered
100units brought up to standard
176,000sqm of retail space
Scope & approach

How the programme ran

Risk-prioritised EPC programme

Working with Pradera Lateral and managing agents Savills, we arranged access to each unit in risk priority order and undertook 200 EPCs.

Audit and risk assessment

Auditing all buildings let with F and G ratings, and risk-assessing those potentially rated F or G.

MEES study

Quantifying costs and exemptions ahead of the deadline, with recommended upgrades where appropriate.

Challenges

What made this difficult

01

Scale and access

Plant running outside occupancy schedules, with control settings drifting through seasonal change and manual overrides.

02

Mixed compliance status

Plant running outside occupancy schedules, with control settings drifting through seasonal change and manual overrides.

03

Hard deadline

Plant running outside occupancy schedules, with control settings drifting through seasonal change and manual overrides.

Results

The outcome

100 units were brought up to standard as part of a staged delivery completed ahead of the February 2023 deadline, bringing every unit in the centre into EPC compliance with the updated MEES regulations.

200EPCs delivered
100units brought up to standard
176,000sqm of retail space
What we learned

Lessons

Takeaways
  • Sequencing by risk and lease event beats working alphabetically through a portfolio
  • Coordination with managing agents is essential for access at scale
  • Complete visibility at every stage keeps a large programme on track